CompTIA PK0-004 Questions Answers
CompTIA Project +- 796 Questions & Answers
- Update Date : January 30, 2026
Prepare for CompTIA PK0-004 with SkillCertExams
Getting PK0-004 certification is an important step in your career, but preparing for it can feel challenging. At skillcertexams, we know that having the right resources and support is essential for success. That’s why we created a platform with everything you need to prepare for PK0-004 and reach your certification goals with confidence.
Your Journey to Passing the CompTIA Project + PK0-004 Exam
Whether this is your first step toward earning the CompTIA Project + PK0-004 certification, or you're returning for another round, we’re here to help you succeed. We hope this exam challenges you, educates you, and equips you with the knowledge to pass with confidence. If this is your first study guide, take a deep breath—this could be the beginning of a rewarding career with great opportunities. If you’re already experienced, consider taking a moment to share your insights with newcomers. After all, it's the strength of our community that enhances our learning and makes this journey even more valuable.
Why Choose SkillCertExams for PK0-004 Certification?
Expert-Crafted Practice Tests
Our practice tests are designed by experts to reflect the actual PK0-004 practice questions. We cover a wide range of topics and exam formats to give you the best possible preparation. With realistic, timed tests, you can simulate the real exam environment and improve your time management skills.
Up-to-Date Study Materials
The world of certifications is constantly evolving, which is why we regularly update our study materials to match the latest exam trends and objectives. Our resources cover all the essential topics you’ll need to know, ensuring you’re well-prepared for the exam's current format.
Comprehensive Performance Analytics
Our platform not only helps you practice but also tracks your performance in real-time. By analyzing your strengths and areas for improvement, you’ll be able to focus your efforts on what matters most. This data-driven approach increases your chances of passing the PK0-004 practice exam on your first try.
Learn Anytime, Anywhere
Flexibility is key when it comes to exam preparation. Whether you're at home, on the go, or taking a break at work, you can access our platform from any device. Study whenever it suits your schedule, without any hassle. We believe in making your learning process as convenient as possible.
Trusted by Thousands of Professionals
Over 10000+ professionals worldwide trust skillcertexams for their certification preparation. Our platform and study material has helped countless candidates successfully pass their PK0-004 exam questions, and we’re confident it will help you too.
What You Get with SkillCertExams for PK0-004
Realistic Practice Exams: Our practice tests are designed to the real PK0-004 exam. With a variety of practice questions, you can assess your readiness and focus on key areas to improve.
Study Guides and Resources: In-depth study materials that cover every exam objective, keeping you on track to succeed.
Progress Tracking: Monitor your improvement with our tracking system that helps you identify weak areas and tailor your study plan.
Expert Support: Have questions or need clarification? Our team of experts is available to guide you every step of the way.
Achieve Your PK0-004 Certification with Confidence
Certification isn’t just about passing an exam; it’s about building a solid foundation for your career. skillcertexams provides the resources, tools, and support to ensure that you’re fully prepared and confident on exam day. Our study material help you unlock new career opportunities and enhance your skillset with the PK0-004 certification.
Ready to take the next step in your career? Start preparing for the CompTIA PK0-004 exam and practice your questions with SkillCertExams today, and join the ranks of successful certified professionals!
Related Exams
CompTIA E2C Project+ Certification Exam
402 Questions
CompTIA Project+ Certification (2025)
386 Questions
CompTIA PK0-004 Sample Questions
Question # 1Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
A. Determine the flexibility between the project constraints
B. Hold a kick-off meeting with the project team
C. Determine procurement needs to meet the project demands
D. Create the risk register
Question # 2
Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?
A. Resources
B. Requirements
C. Scope
D. Funding
Question # 3
A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)
A. Update the project charter to include the functional manager as a key stakeholder
B. Publish the project schedule to the functional manager
C. Review the communications plan to ensure proper involvement
D. Add the incident to the issue log and seek resolution
E. Ensure the functional manager is on the status report distribution list
Question # 4
A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation?
A. Meeting minutes
B. Issue log
C. Project schedule
D. Budget
Question # 5
A project manager is assigned a project that is part of the company’s strategic objectives. Of which of the following is the project a part?
A. Project management office
B. Portfolio
C. Program
D. Mission statement
Question # 6
A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an:
A. RTM
B. RFQ
C. RFI
D. RFP
Question # 7
A project team is working on a project with high public visibility and excitement. The project sponsor is concerned the public may lose interest due to the long delivery timeline. Which of the following is the BEST way to keep the external stakeholders informed and engaged throughout the project?
A. Video conferencing
B. Instant messaging
C. Social media
D. Email
Question # 8
Which of the following represents the order of the team development stages?
A. Forming, storming, norming, performing
B. Forming, performing, storming, norming
C. Forming, norming, storming, performing
D. Forming, norming, performing, storming
Question # 9
Which of the following should a project manager consider as part of a make or buy analysis?
A. Organization type
B. KPIs
C. Project charter
D. Trade secrets
Question # 10
A project has been experiencing some difficulties due to third-party vendors. The project manager should request.
A. Additional resources
B. A gate review
C. A risk register update
D. A performance audit
Question # 11
Which of the following are characteristics of a matrix organization? (Choose three.)
A. The project manager has full authority.
B. Resources report directly to the functional manager.
C. Authority is shared between functional and project managers.
D. Resources are assigned from functional area to project.
E. There is ad hoc resourcing.
F. The organization utilizes a bench.
G. The project manager authority ranges from strong to weak.
Question # 12
Which of the following organizational structures uses project team members who are selected from within their department?
A. Projectized
B. Balanced matrix
C. Functional
D. Strong matrix
Question # 13
The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?
A. Gantt chart
B. Scatter chart
C. Run chart
D. Process diagram
Question # 14
Which of the following is a risk strategy?
A. Risk quantification
B. Risk avoidance
C. Risk identification
D. Risk review
Question # 15
A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?
A. Regression plan
B. Quality plan
C. Change validation
D. Application version control